This page will provide information for the overall testing timeframe as well as instructions on how to establish connectivity to the ATLAS R2 QA Environment.

Testing Schedule

July 22, 2019 - October 18, 2019: Full Integration Testing (required)

Full Integration Testing – A fully converted production database will be available in the ATLAS R2 QA environment. The database will be refreshed weekly based on a defined schedule (see below). Other than this weekly data conversion process that typically occurs on Sunday evenings, the ATLAS staging environment will be available for web service and batch file testing. Note that technical support on weekends and holidays will be limited.

Batch File Testing

Batch files received via the MOVEit file transfer connection to the ATLAS R2 QA environment will automatically be processed business day evenings. Any files received by 7:00pm (EDT) will be processed and an associated response file will be produced and available in MOVEit.

If you would like to have a file format verified, please contact the interface team with that request at DOT-DL-ATLAS-Interfaces-R2@dot.state.ma.us.

Web Service Testing

Web service endpoint should be responsive 24x7, except for weekend conversion and unexpected issues (it is a testing environment).

Data Refresh Schedule

The ATLAS R2 QA environment will hold a converted copy of the production database. The database will be refreshed from a new converted copy of production on the following schedule:

Testing Cycle Production Data "as of" Refreshed in ATLAS R2 QA on Testing Cycle Begin Date Testing Cycle End Date
1 Wed, Jul 10th Sun, Jul 14th Mon, Jul 22nd Fri, Jul 26th
2 Wed, Jul 10th Sun, Jul 28th Mon, Jul 29th Fri, Aug 2nd
3 Wed, Jul 10th Sun, Aug 4th Mon, Aug 5th Fri, Aug 9th
4 Wed, Aug 7th Sun, Aug 11th Mon, Aug 12th Fri, Aug 16th
5 Wed, Aug 7th Sun, Aug 18th Mon, Aug 19th Fri, Aug 23th
6 Wed, Aug 21st Sun, Aug 25th Mon, Aug 26th Fri, Aug 30th
7 Wed, Aug 21st Sun, Sep 1st Mon, Sep 2nd Fri, Sep 6th
8 Wed, Sep 4th Sun, Sep 8th Mon, Sep 9th Fri, Sep 13th
9 Wed, Sep 11th Sun, Sep 15th Mon, Sep 16th Fri, Sep 20th
10 Wed, Sep 18th Sun, Sep 22nd Mon, Sep 23th Fri, Sep 27th
11 Wed, Sep 25th Sun, Sep 29th Mon, Sep 30th Fri, Oct 4th
12 Wed, Oct 2nd Sun, Oct 6th Mon, Oct 7th Fri, Oct 11th
13 Wed, Oct 9th Sun, Oct 13th Mon, Oct 14th Fri, Oct 18th

NOTE: The Smoke Testing end-point will remain active throughout Interface Testing, and Sample Batch files can be provided upon request.

*Production connectivity verification – October 21st through November 1st

Testing Setup – Batch

Testing via batch file transfer will be established via the RMV’s MOVEit solution. Please contact the MOVEit mailbox (ATLAS.MOVEitproject@dot.state.ma.us) for any issues or questions related to transition of all secure file transfers to the MOVEit solution. For more information please visit the MOVEit information page.

Testing – Web Service

ATLAS web services will be secured by both IP whitelisting and certificate authentication. To establish web service connectivity to the ATLAS staging environment for testing, each organization will need to provide:

  • All IPs from which ATLAS web service calls could originate.  These IPs will be included in the RMVs whitelist.  IPs that attempt to access the ATLAS endpoint that are not listed will be blocked.
  • A Client Certificate – A 2-year client certificate public key signed by a Certification Authority.

(for more information, please review this updated ATLAS Web Service Security document which included and Overview, X.509 Client Certificates, and Client IP Whitelisting requirements)

Generating a Sample Request

This new document is intended to serve as a supplement to web service consumers by providing easy ways to generate a sample request. – MA RMV ATLAS – Generating Web Service Sample Requests

Please download and complete this form to provide IPs for whitelisting IPM Web Service Testing Setup.

Please send completed ATLAS/IPM Release 2 Testing form & Client Certificate information to tedford.armistead@dot.state.ma.us.

Testing Strawman

To provide input to the IPM community, the RMV has developed the following IPM Testing Strawman document which provides input on minimal testing for the IPM transaction processing. This was discussed during the latest IPM webinar (#6).

ATLAS R2 IPM Testing Strawman (posted 8/23/2019)